These charts
were used
to analyze activity cost and activity time. The department managers were surprised to
discover that the most expensive activity was research. Research cost for items
that are paid on time is a needless expense.
The company's internal procedures
required this research activity. It seemed fine and prudent. But this policy was
made without the knowledge of what it would cost. Their AIM activity based cost project discovered
it's annual cost was $202,000 (4 FTE's).
The company revised their
procedures and stopped conducting research on all items under 60 days. This,
and 4 other simple changes, reduced costs by more than $350,000 within the first
6 months. These savings were realized through headcount reductions as people
were lost through attrition.
This ABC
project was conducted over 10 weeks at a cost of $26,000. It delivered over 160
chart and graph
reports from these ABC (activity based cost) models:
- Staffing Model
- Process Cost Model
- Activity Cost Model
- Payment Value Model
- Age of Item Model
- Customer Segment Cost Model
- Computer System Utilization Model

This chart provides
the detail of all activity hours, cost and percent. The format is very useful
for Activity Based Costing analysis and reporting models.
|
Activity Hours, Cost & Percent for 0-60 days items |
|
|
|
Hours |
Cost |
% |
|
|
Total |
54,081 |
$1,459,623 |
|
|
|
Researching |
7,489 |
$202,134 |
13.848% |
|
|
Book Maint |
5,499 |
$148,409 |
10.168% |
|
|
Raise discrep |
5,243 |
$141,494 |
9.694% |
|
|
Payment Entry |
3,429 |
$92,556 |
6.341% |
|
|
Inbound call |
2,720 |
$73,407 |
5.029% |
|
|
Clean up |
2,404 |
$64,896 |
4.446% |
|
|
Notate Initial List |
2,345 |
$63,300 |
4.337% |
|
|
AE |
2,306 |
$62,236 |
4.264% |
|
|
Outbound call |
2,129 |
$57,449 |
3.936% |
|
|
E-mail |
1,872 |
$50,534 |
3.462% |
|
|
Other Communication |
1,853 |
$50,002 |
3.426% |
|
|
Update Workstation Notes |
1,518 |
$40,959 |
2.806% |
|
|
Notate 50K List |
1,478 |
$39,895 |
2.733% |
|
|
Follow-up 2nd request |
1,202 |
$32,448 |
2.223% |
|
|
Clean up/prep to send |
1,183 |
$31,916 |
2.187% |
|
|
Reconcile |
1,104 |
$29,788 |
2.041% |
|
|
Clean up/prepare to send |
1,064 |
$28,724 |
1.968% |
|
|
Disbursement |
946 |
$25,533 |
1.749% |
|
|
Completion of form |
808 |
$21,809 |
1.494% |
|
|
Other Book Maintenance |
729 |
$19,682 |
1.348% |
|
|
Review Potential Cancel List |
670 |
$18,086 |
1.239% |
|
|
Other Cash Procg Stmt/DO |
532 |
$14,362 |
0.984% |
|
|
Other Discrepancies |
512 |
$13,830 |
0.948% |
|
|
Balance |
473 |
$12,766 |
0.875% |
|
|
Follow-up |
453 |
$12,234 |
0.838% |
|
|
Other Admin Tasks |
434 |
$11,703 |
0.802% |
|
|
Other Cash Processg Book Cash |
374 |
$10,107 |
0.692% |
|
|
Training with Buddy |
363 |
$10,107 |
0.692% |
|
|
800 line calls- inbound |
355 |
$9,575 |
0.656% |
|
|
Expensing |
276 |
$7,447 |
0.510% |
|
|
Other A/C |
237 |
$6,383 |
0.437% |
|
|
Balance A/C |
221 |
$5,851 |
0.401% |
|
|
Follow-up 3rd request or more |
217 |
$5,744 |
0.401% |
|
|
Other Cancellation |
210 |
$5,559 |
0.401% |
|
|
Statement |
179 |
$4,772 |
0.328% |
|
|
Acct Current |
175 |
$4,665 |
0.328% |
|
|
Faxing/mailing |
148 |
$3,946 |
0.255% |
|
|
Voice Mail |
138 |
$3,724 |
0.255% |
|
|
Complete form |
118 |
$3,680 |
0.219% |
|
|
Other Statement |
99 |
$2,639 |
0.146% |
|
|
Update run-off date |
89 |
$2,373 |
0.146% |
|
|
Filing |
79 |
$2,106 |
0.146% |
|
|
Review Cancel Paid/Clear List |
59 |
$1,596 |
0.109% |
|
|
Other Reinstatement |
49 |
$1,572 |
0.109% |
|
|
Complete Transmittal |
41 |
$1,093 |
0.109% |
|
|
Other Training |
39 |
$1,040 |
0.109% |
|
|
Other Meeting |
34 |
$1,003 |
0.109% |
|
|
Other initial list |
31 |
$906 |
0.073% |
|
|
Complete 552 |
29 |
$773 |
0.036% |
|
|
Prepare documentation |
23 |
$613 |
0.036% |
|
|
Escheat |
20 |
$582 |
0.036% |
|
|
Posting |
19 |
$531 |
0.036% |
|
|
Conference Call |
16 |
$583 |
0.036% |
|
|
|
|
|
|
|
Our experience conducting ABC
(activity based costing) projects with more than 500 organizations has
consistently achieved similar results.
Let us know how you'd like to learn how our
AIM Activity based costing models will help you reduce costs and improve
performance.
Learn with a free ABC pilot
Request an Activity Based Costing Webinar |